Industrial and commercial photovoltaic power generation grid-connected projects Online power quality detection device, arc island protection device data acquisition case

 一、Project background and requirements

Project location: Luyang District, Hefei, Anhui

Project background: Photovoltaic power generation grid-connected project equipment monitoring

In order to realize the real-time collection of meter data, power quality analysis equipment data, arc island protection equipment data, and effectively monitor electrical data, real-time monitoring is achieved. Low cost, simple wiring, and wireless transmission methods are used to realize data collection.

1、State Grid electricity meter data collection, real-time collection, and remote monitoring.

2、the online power quality detection device (Nanjing Canneng, model: NBQS-581) and the arc island protection device (Kezi Electric Power, model: KZB-300F ) requires complicated conventional wiring methods, and the site does not support the prerequisite for large-scale wiring implementation.


 


 

 

Power quality online monitoring device

 

 

 




 

 

 

 

 

 

 

Corresponding to the equipment that needs to be collected

二、Project technical solution

Overall implementation of technical solution architecture:


 

Figure 2: Overall implementation plan

For electric meters, we use our main 4G infrared meter reading product ( SC-GP-IR4G) to achieve non-immersion installation and collection



 

 

 

 

 

 

 

 

 

Electricity meter collection solution

For the online detection device of power quality and arc island protection device, data collection is carried out through the 485 communication port of the original equipment, and is implemented with our company's 4G wireless data acquisition terminal (SC-GP-GWRTU).



 

 

 

 

 

 

 

 

 

Figure 4 : Arc island protection and power quality monitoring equipment collection scheme


 

Power quality monitoring collection parameters

三、On-site implementation process and installation docking

3.1 Electricity meter data collection

The meter data collection connection is relatively simple. The probe is fixed, the power is collected by the collection equipment, and after the technical remote debugging protocol, the meter data can be collected in real time.



 

 

 

 

 

 

 

 

 

 

 

 

 

Electricity meter collection implementation diagram

3.2 Online power quality detection device and arc island protection device


Determine the 485 communication port of the device to be collected, ensure that the collector can collect data through the 485 communication interface, and then connect on-site.

 

 

 

 

 

 

 

 

 



 

 

On-site 485 communication wiring diagram

The communication interface line of the collection equipment is fixed, and after the collector is fixed and installed, it is powered on site. The matching suction cup antenna needs to be placed in an open position to avoid the confined environment affecting the 4G signal transmission.

 

 



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

On-site collector installation wiring diagram

 

 

四、Implement data collection and final presentation


Our 4G infrared meter reading products and 4G wireless data collection terminals are equipped with a dedicated data viewing cloud platform (Figure 8, Figure 9, Figure 10)

.

 

 

 

 

Electric meter data background display

 

 

 

 

 

 

 




 

 

 

 

 

 

 

 

 

 

 

 

 

 


Power quality monitoring background data display

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arc protection island device background data display

评论

此博客中的热门博文

DAQ-IOT Modbus RTU RS485 Split Core Current Transformer CT AC Analog Signal Coil Sensor DC 12V 5A DC Current Transformer Power On or Off Status Monitoring

Construction of Groundwater Monitoring and Intelligent Management and Control System Based on Internet of Things and Digital Twin Technology

DAQ-IOT 4G NB-IOT LoRa WiFi CT Electrification Undamage Installation Wireless Micropower Consumption Current Temperature Measurement Acquisition Terminal